Site: Christmas Creek Mine
Client: Fortescue Metals Group (FMG)
Service: SMP
Capability: Maintenance, Project Services
Industry: Mining and Resources
Scope of works
FMG enlisted Breight Group to replace the structural beams in the TLO (Temporary Loading Out) area at their Christmas Creek mining site. Key activities included installing temporary handrails and boarding for SIMOPS, removing existing beams, and the precision welding of new cleats to ensure structural integrity before Breight Group’s specialised workforce then set about efficiently installing all new beams, securing grating, and touch-up painting in a complete end to end maintenance service.
The entire process, from installation to QA documentation sign-off, was completed on time (can we give exact time?), safely, and without incidents. All temporary handrails and boarding were carefully removed upon completion.
Under Breight Group’s expert management, the project was executed seamlessly, adhering to the highest safety and efficiency standards the company has come to be known for. Full compliance with the QA management plan was maintained, with thorough non-destructive testing (NDT) ensuring the quality and integrity of all work completed. This project demonstrated Breight Group’s commitment to high-quality site maintenance, structural integrity, and professional mining labour hire for FMG operations
Key Activities Completed
- Installation of temporary handrails and boarding for SIMOPS
- Remove old beams
- Remove and weld on new cleats
- Complete NDT as per QA management plan
- Installation of new beams
- Complete QA documentation for sign off
- Touch up painting Install and secure grating
- Remove temporary handrails and boarding