Screen House Upgrade

Site: Cape Lambert

Client: Rio Tinto

Service: Structural, Mechanical & Piping, Rope Access

Capability: Project Services, Planning

Industry: Mining and Resources

Scope of Work:

Breight Group was engaged by Rio Tinto to undertake a comprehensive upgrade of the Screen House at the Cape Lambert site. The project involved replacing liners and conducting structural repairs across six screens, all while adhering to a tight shutdown schedule over an 8-month period.

The scope of work encompassed several critical tasks. The team started by removing the rotable chutes and replacing the worn liners. Structural repairs were carried out on various beams using Rope Access technicians, ensuring minimal disruption and optimal safety. Non-destructive testing (NDT) was performed to verify the integrity of the work completed. After the structural repairs and liner replacements were completed, the rotable chutes were reinstated, and the system was fully commissioned.

Throughout the project, we ensured that all work was conducted within the specified timeframes and safety standards. Comprehensive quality documentation were provided, maintaining transparency and ensuring the project met the client’s requirements. The entire upgrade was executed without incidents, showcasing Breight Group’s commitment to safety, quality, and efficiency in completing complex maintenance tasks in challenging environments.

Key Activities Completed:

  • Removal and replacement of rotable chutes and worn liners
  • Structural repairs on beams using Rope Access technicians
  • Non-destructive testing (NDT) to verify work quality
  • Reinstatement of chutes and system commissioning
  • Comprehensive quality documentation and final sign-off
  • Successful completion of the project within the time constraints and with zero incidents